Exercise 14-32 |
|
|
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
|
|
Insert your answers into the gray-shaded cells. If an answer is incorrect, the |
|||||||||
|
word “wrong” will appear. |
|
|
|
|
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
a. |
Value-added time |
÷ |
Total time |
= |
MCE |
|
|
|
||
|
|
50,400 |
|
1,44,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b. |
|
|
|
|
|
|
Process |
|
|
|
|
|
Total units |
÷ Value-added time = |
productivity |
|
|
||||
|
|
33,60,000 |
|
50,400 |
|
|
units per hour |
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
c. |
|
|
|
|
|
|
Process |
|
|
|
|
|
Good units |
÷ Total units = |
quality yield |
|
|
||||
|
|
29,23,200 |
|
33,60,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
d. |
|
Good units |
÷ |
Total time |
= |
Throughput |
|
|
||
|
|
29,23,200 |
|
1,44,000 |
|
|
units per hour |
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
e. |
What can company management do to raise hourly throughput? |
|
|
|||||||